B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Unity Comox Valley hosts serenity service in Comox Thursday

Do you have mixed feelings about the holidays? Unity offers a special… Continue reading

UPDATE: RCMP involved in crash south of Courtenay Saturday night

An RCMP member was involved in a three-vehicle collision on Highway 19… Continue reading

Mental health advocate’s journey with dissociative identity disorder sparks conversation

Coast Mental Health Courage to Come Back Awards nomination deadline Jan. 31

Assisted living workers allegedly attacked while picketing

BCGEU president Stephanie Smith says arrows and gasoline were thrown at the picketers early in the week

Dangerous drug confirmed in the Comox Valley

Lab test confirms the presence of fentanyl in powder substance

VIDEO: This B.C. school leads country in vaccine donations to UNICEF

Federally funded Kids Boost Immunity uses quizzes to earn vaccinations

Boeser scores 3, Pettersson has 5 points as Canucks hammer Blues

Vancouver picks up impressive 6-1 win in St. Louis

B.C. police stop drunk driver who offered up burger instead of ID

Roadblock checks over the weekend found at least two other impaired drivers

In Canada, the term ‘nationalism’ doesn’t seem to have a bad rap. Here’s why

Data suggest that Canadians don’t see the concept of nationalism the way people do in the United States

Small quake recorded west of Vancouver Island

No injuries or tsunami warning after 5.4 rumble felt some 400 kilometres from Victoria

B.C. suspends Chinese portion of Asian forestry trade mission due to Huawei arrest

Huawei’s chief financial officer Meng Wanzhou was detained at the request of U.S. in Vancouver

Canadians spent $1.7 billion dollars online in December 2017

Online retail sales accounted for 3.4 per cent of total retail sales

2-year investigations nets $900,000 in refunds for payday loan customers

Consumer Protection BC says selling practices were ‘aggressive and deceptive’

China: Canada’s detention of Huawei exec ‘vile in nature’

Huawei is the biggest global supplier of network gear for phone and internet company

Most Read