B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Basket raffle a Comox Valley Child Development Association Children’s Telethon tradition

One-stop Christmas shopping with Winner Takes All Basket rffle

Comox Valley gives back

A look at some of the organizations and individuals who help out in the community

Golden anniversary for G.P. Vanier Thursday

It was a day of celebration for students, educators and administrators past… Continue reading

Comox Valley RCMP seeking witnesses of attempted sexual assault

The Comox Valley RCMP is looking for witnesses after an attempted sexual… Continue reading

Tommy Chong says cannabis legalization makes him proud to be a Canadian

Legendary marijuana advocate and comedian celebrates cultural milestone at Kelowna event

Comox Valley gives back

A look at some of the organizations and individuals who help out in the community

B.C. passenger caught smoking weed in a car issued $230 fine

Saanich police did a field sobriety test on the driver and deemed it safe for him to drive

Payette invites critics to ‘come and spend a few days’ with her

Governor General Julie Payette made her first official to B.C. back in March

More pot stores expected in B.C. in coming ‘weeks and months’: attorney general

Attorney General David Eby and Public Safety Minister Mike Farnworth visited the new BC Cannabis Store in the province’s Interior

Telus launches charitable foundation to help vulnerable youth

The Telus Friendly Future Foundation complements other social initiatives by the company, including Mobility for Good

Police say suspicious death of B.C. artist ruled a homicide

Patrick Zube Aylward’s body was found in a residence on a rural road outside of Seton Portage, west of Lillooet, B.C.

Temporary roads being built in areas affected by landslide in northern B.C.

Emergency Management BC news release says Disaster Financial Assistance is available to eligible residents of the Peace River Regional District who may have been affected by the landslides

B.C. tickets win big in Lotto Max draw

Jackpot carried over; B.C. tickets share Max Millions prizes

Most Read