Premier Christy Clark and BC Hydro CEO Jessica McDonald announce main contractor for Site C dam construction at a BC Hydro substation in Burnaby Wednesday.

Contractors picked for Site C construction

Samsung of Korea, ACCIONA of Spain and Petrowest to sign BC Hydro's biggest-ever construction contract for Peace River dam

BC Hydro has selected its main contractor to construct the third dam on the Peace River, and is finalizing a $1.5 billion contract for a dam and river diversion that is the largest in the utility’s history.

The three members of Peace River Hydro Partners are Korean engineering and electronics giant Samsung, Spanish dam and infrastructure specialist ACCIONA and Petrowest Corp., a Calgary-based company that has expanded from oil and gas construction to large infrastructure in northeast B.C. and Alberta.

Petrowest and ACCIONA worked on the recently completed Fort St. John hospital, and ACCIONA has built hydro dams in Spain and Chile. Samsung has built hydro dams, roads, buildings, tunnels, bridges and airports.

Energy Minister Bill Bennett said the contract will be for a fixed price to build the main “civil works,” which include excavation, river diversion tunnels, intake and outlet structures, a kilometre-long earth-filled dam, a 70-metre-high concrete buttress and a road network.

Bennett said work can proceed in winter, and he is confident BC Hydro can stay within its estimated project cost of $8.3 billion.

When the decision to proceed was made a year ago, oil and gas activity was high and there were concerns about labour shortages. But with a continuing slump in oil, natural gas and mineral prices, there are idled workers and equipment in Fort McMurray and other sites in Western Canada.

“Mining is really slow right now and LNG has not yet taken off, so you actually have almost a perfect circumstance for BC Hydro to be entering into its major contracts on Site C,” Bennett said.

Petrowest CEO Rick Quigley said the project will hire locally first, from around B.C. second and elsewhere in Canada third before looking outside the country for skilled labour.

BC Hydro also identified Peace River Hydro Partners’ labour agreements with Christian Labour Association Canada and Construction Maintenance and Allied Workers’ Canada, which broke away from the U.S. international carpenters’ union in 2007.

B.C. Building Trades executive director Tom Sigurdson issued a statement protesting the choice.

“Premier Clark has long said that B.C. workers should be the first in line for Site C work,” Sigurdson said. “This has not been the case so far under the first major contract, awarded to a large Alberta company which has one of four workers on site from out of province.”

 

Just Posted

Crews begin cutting down 100-year-old Comox willow tree

The tree was determined to be unhealthy and is being cut down due to safety concerns

Best of World Community Film Fest screens Tuesday

The votes are in from the recent World Community Film Festival and… Continue reading

Merville resident looking for help to name original settler families

Janice Isenor is hoping to figure out which families settled where in Merville 100 years ago

Cultural sharing for Comox Valley School District song unveiling

After nearly a year in the making, a special gift was presented… Continue reading

Union Bay Improvement District board apologizes to trustee; deadline remains for other demands

UBID board complies with one of the demands of a letter threatening legal action

B.C. students win Great Waters Challenge video contest

Video, mural and song about saving the salmon claims the top prize

Eight cases of measles confirmed in Vancouver outbreak

Coastal Health official say the cases stem from the French-language Ecole Jules Verne Secondary

Ontario police field complaints over Amber Alert for missing girl, 11, found dead

Some said the Amber Alert issued late Thursday for Riya Rajkumar disrupted their sleep

Former B.C. premier Gordon Campbell accused of sexual touching

Accuser went to police, interviewed by Britian’s Daily Telegraph

B.C. couple attacked with acid, slashed with knife in Vietnam

Warning, graphic images: Man has burns on 80 per cent of his body, slashed with knife

Northern B.C. First Nation clan says ancient tools found at pipeline work site

Archeologists from the Smithsonian Institute estimate one of the stones found dates back up to 3500 years

Diver discovers possible historic anchor off Campbell River

“This is an anchor I believe to be from a Spanish galleon.”

Names keep adding to vaccine petition started by B.C. mom

Maple Ridge mom started campaign to make vaccination a condition of attending school

Most Read