Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Comox Valley medical cannabis business growing despite impending legalization

With nearly a month to go until new cannabis legalization laws come… Continue reading

Humpback whales visit Cape Lazo

Peter Hamilton with Lifeforce Ocean Friends snapped these photos of some humpback… Continue reading

Valley Father-daughter duo share a special bond over a kidney

Annual kidney walk is set for Sept. 23 at Simms Park

Stolen Victoria vehicle crashes in Black Creek

On Sept. 15, 2018 at approximately 10:45 p.m., the Comox Valley RCMP… Continue reading

Courtenay getting a tool library

New facility allows do-it-yourselfers to borrow tools

VIDEO: Messages of hope, encouragement line bars of B.C. bridge

WARNING: This story contains references to suicide and may not be appropriate for all audiences.

Fresh-faced Flames fend off Canucks 4-1

Vancouver drops second straight NHL exhibition contest

Scheer pushes Trudeau to re-start Energy East pipeline talks

Conservative Leader Andrew Scheer questioned the Prime Minister over Trans Mountain project

Mistaken identity: Missing dog claimed in Moose Jaw belongs to another family

Brennen Duncan was reunited with a white Kuvasz that was found in Saskatchewan

Abandoned kitten safe and sound thanks to B.C. homeless man

‘Jay’ found little black-and-white kitten in a carrier next to a dumpster by a Chilliwack pet store

Police chief defends controversial marijuana seizure

Advocates said cannabis was part of an opioid-substitution program in Vancouver’s Downtown Eastside

VIDEO: B.C. deer struggles with life-preserver caught in antlers

Campbell River resident captures entangled deer on camera

Trans Mountain completes Burrard Inlet spill exercise

Training required, some work continues on pipeline expansion

Most Read