Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

‘LNG, Fracking and the Comox Valley Connection’ – public forum in Courtenay

Wednesday, Feb. 27, 7 p.m. at the Florence Filberg Centre

UPDATE: Police determine no emergency in Friday’s mystery radio appeal for help

Police had asked for help following mysterious signals from somewhere between Comox and Sayward

Comox Valley child gets dream vacation from Make-A-Wish Foundation

Elliot Hunter went to Disneyland and met Lightning McQueen

UPDATED: Two vehicles seen leaving bloody scene of Courtenay shooting

32-year-old victim in stable condition and known to police

Courtenay to host the BC Regionals FireFit Championships

‘Toughest two minutes in sports’ coming to the Comox Valley

Indigenous leaders, politicians say Trans Mountain report flawed

The National Energy Board has endorsed an expansion of the Trans Mountain pipeline a second time

Have you heard the legend of Shuswaggi, the Shuswap Lake monster?

Witness accounts as old as 1904, and as recent as 2018, place a creature in the lake’s depths

Credit card fraud steals $50,000 from Victoria businesses: police

Crime Reduction Unit investigating several frauds costing several businesses over $50,000

UPDATE: B.C. ticket holder winner of $25.9-million Lotto Max jackpot

Next draw set for Mar. 1 with an estimated jackpot of $10 million

B.C.-based ‘Team Tardi’ brings home gold in junior curling worlds

In a 9-4 victory over Switzerland, a Langley-based curling team earned its 2nd straight world title

People gather for funeral of seven children killed in fast-moving Halifax fire

Traditional portion of the service will be followed by words from community members

B.C. weavers to help Alaska Native project honouring survivors of violence

Dozens of Chilkat and Ravenstail weavers from all over North America will be weaving 5-inch-by-5-inch squares

Towhees advance to 3A final, B.C. tourney

Ice still in hunt for coveted third spot

B.C. skip Sarah Wark and team eliminated at Scotties Tournament of Hearts

Nontheless pretty impressive stuff from the 24th-ranked team in the country

Most Read