Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

Girl heard saying ‘Help my Dad’ in suspicious radio message: Campbell River RCMP

Police asking for help following mysterious signals from somewhere between Comox and Sayward

Comox Valley child gets dream vacation from Make-A-Wish Foundation

Elliot Hunter went to Disneyland and met Lightning McQueen

UPDATED: Two vehicles seen leaving bloody scene of Courtenay shooting

32-year-old victim in stable condition and known to police

Courtenay to host the BC Regionals FireFit Championships

‘Toughest two minutes in sports’ coming to the Comox Valley

Spring fishery closures mulled for south coast

Fewer fish are returning to rivers and more conservation needed, say feds

National Energy Board approves Trans Mountain pipeline again

Next step includes cabinet voting on the controversial expansion

Reports of rashes prompt closure of all Harrison Hot Springs pools

Public pool available after Fraser Health shut down all five mineral pools until further notice

Two more measles cases confirmed in Vancouver

It brings the number of total cases within the city connected to the outbreak to ten

B.C. Special Olympics officially underway in Vernon

Athlete’s Oath: “Let me win. But if I cannot win, let me be brave in the attempt.”

Vancouver Aquarium wants your help to name a baby killer whale

The public helped name Springer’s first calf, Spirit, and is being asked to help with the second

Guards protest firing of fellow officers charged with assault at B.C. prison

Corrections officers demonstrated in Maple Ridge on Friday afternoon

Skier dies at Revelstoke Mountain Resort

Cause of death for young man has not been released

R. Kelly charged with 10 counts of sexual abuse

R&B star has been accused of sexual misconduct involving women and underage girls for years

Most Read