G.P. Vanier in Courtenay. Circa 2018. Photo courtesy Comox Valley Schools

G.P. Vanier upgrades more than $1.4 million over budget

The original construction budget was not adjusted to account for some expenses

Following the completion of the Georges P. Vanier seismic upgrades in October, the school district determined they had gone approximately $1,450,000 over budget.

The $33.1 million upgrade project started in 2016 and was completed in phases, including adding additional classrooms, specialized spaces such as a new auditorium and an Aboriginal education room, and relocating the library. The project also included upgrading the school’s mechanical and electrical systems that were nearly 50-years-old. Approximately $32.8 million for the project was provided by the Ministry of Education and around $1 million was from the school district.

According to SD71 secretary-treasurer Nicole Bittante, the school district did not realize they were over budget until the project was completed as they thought all expenditures had been accounted for.

“While this overspend was not identified until the project was completed, it was thought all along that the budget allowed for these expenditures,” said Bittante. “District staff were reconciling all of their amounts to the original budget. In the meantime, the original budget hadn’t been adjusted for various items. So it appeared during the term of the project that the project was on schedule and on budget.”

Bittante outlined the areas where the overspending happened, with the most significant portion being the GST.

“The original construction budget back in 2015 that was provided to the construction company did not include GST, however, the budget should have included the non-rebatable portion of GST,” she said. “There’s a portion that the district pays and then receives back in a rebate.”

The non-rebatable portion of GST was a cost to the district of approximately $477,000.

Other areas where there was overspending included a portion of the director of operations’ salary and some wages for a custodian which were not reduced from the construction budget, totaling $196,000.

In 2017, the gymnasium walls required repairs due to a safety concern, and while the Ministry provided $220,000 to address the issue, the fix still went $117,000 over budget.

The costs for the initial project planning, totaling approximately $152,000, were also not removed from the construction budget. Another $40,000 was listed as “other balancing factors,” and the project went an additional $465,000 over budget as this amount was not covered by the risk reserve.

“The $33 million included a $4 million risk reserve. It wasn’t guaranteed funding, it was an amount that was awarded through the ministry, but it was an amount that we had to apply for and there were criteria attached to it,” said Bittante. “I think the issue is that we, in our budget, gave the $4 million to the construction company and it was spent.”

The school district was only able to access approximately $3.5 million of the $4 million with the rest being a cost to the district.

Bittante clarified that the overspending was not a reflection of the contractor as they came in on budget. Their budget just should have been smaller.

“They came in on target with money that they were given, but we weren’t able to access all the funds.”

She adds that increased oversight will occur on all future capital projects to ensure any overspending is identified and taken care of immediately.

At Tuesday’s meeting, the SD71 school board voted in favour of transferring $1,450,000 of unrestricted operating surplus to cover the overspend.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Comox Valley Regional District asks residents about curbside pickup

Online survey about waste pickup for most rural residents runs until Sept. 11

Independent home learning hub to open for kids in the Comox Valley

Community’s Waldorf team put Daily Wonder together to help students, families

Nanwakolas Council makes donation to North Island College to support First Nation students

The money was raised at the 2019 Nanwakolas golf tournament.

North Island College launches virtual orientation

New and returning North Island College students are being welcomed to the… Continue reading

371 British Columbians battling COVID-19, health officials confirm

Thursday (Aug. 6) saw a second straight day of nearly 50 new confirmed cases

Cowichan RCMP use spike belts to end car chase — man in custody

The driver was arrested at the scene a short distance from his vehicle

COVID-19 tests come back negative for remote First Nation

“There are no suspected cases in the community at this time.”

Visitors and non-residents entering closed remote B.C. First Nation’s territories

With limited resources, they say they don’t have any authority or power to enforce the closures

UBC loses appeal on Fisheries Act convictions

BC Supreme Court upholds order to pay $1.55-million fine

Masks to be mandatory on BC Transit, TransLink starting Aug. 24

Both BC Transit and TransLink made the announcement in separate press releases on Thursday

Acclaimed B.C. actor Brent Carver passes away

Carver, one of Canada’s greatest actors with a career spanning 40 years, passed away at home in Cranbrook

B.C. would not send students back to school if there was ‘overwhelming risk’: Horgan

Plan has left many parents across the province worried about their children’s safety

Most Read